Why are commuter buses now running down West 39th Street between Ninth and Tenth Avenues? Since October 15, buses coming out of the Lincoln Tunnel go up the Dyer Avenue bus lane, onto a new slip ramp, down to West 39th, west along the block, and back into the ramp system near the northeast corner of 39th and Tenth. The Port Authority's October 13 advisory explains why. The ramps that used to carry those buses sit inside the footprint of a future storage and staging facility, so they have to come out before anything new can go up.
The detour shows how the $11 billion project reaches the blocks around Dyer Avenue. Demolition, lane closures and overnight shifts are happening now. The promised public open space comes after a new terminal on Eighth Avenue, which the Port Authority schedules for 2035.
What Changed on West 39th
General traffic on West 39th between Ninth and Tenth is now restricted. Local vehicles and vehicles serving the businesses on that block can still use it. At Tenth Avenue the lanes have been reconfigured so buses enter the ramp system from the north lane without stopping at the light. Local traffic uses a south lane to go straight or turn right onto Tenth. Pedestrians and cyclists still use the block, but the walkway and bike lane have moved south to make room. amNewYork's October 14 report described the same setup.
The detour also brings extra buses to nearby streets. The Port Authority's October 30 weekly travel advisory warned of heavier-than-normal bus traffic on West 40th between Galvin Avenue and Ninth, on Ninth Avenue between 40th and 39th, and on West 39th between Ninth and Tenth, with traffic enforcement agents assisting. The morning exclusive bus lane is unaffected because it uses a different ramp.
The Ramp Behind the Detour
The ramp being removed is E-96. It used to take buses into the terminal from Dyer Avenue as they left the Lincoln Tunnel, and from 40th Street. According to the October 16 community construction update, the contractor, Tutor Perini, is taking it out in three sections starting on or about October 24, with work continuing through the rest of the year.
Each section comes apart in two steps, concrete removal followed by steel removal, and the two sound different. Daytime shifts include limited hoe ramming to break apart the joints between ramp sections. Overnight crews saw-cut the roadbed and use a newer method called coring, which drills holes so cranes can lift sections out. The Port Authority describes both saw cutting and coring as quieter than older demolition methods, and sound-absorbing blankets surround the worksite.
The update sets two dates. Most of the concrete is expected out by mid-December, and the steel beams by the end of 2026. The Port Authority says noise should drop as the work moves from concrete to steel and hoe ramming tapers off. Lifting out the steel beams is overnight crane work that it expects to produce low noise levels. For anyone whose windows face Dyer Avenue, mid-December is the date to watch.
The Overnight Closures Through Year-End
The ramp work requires street closures, and most of them happen after dark. These are the windows the Port Authority has published:
| Street segment | Closure | Window | Scheduled through |
|---|---|---|---|
| West 40th, Dyer Ave to 10th Ave | Full overnight closure, up to five nights a week | 9 p.m. to 6 a.m. | The rest of 2026 |
| 10th Ave, 39th to 40th St | Full overnight closure for steel placement | 11 p.m. to 5 a.m. weeknights, 1 a.m. to 7 a.m. Friday to Sunday | About November 15 |
| West 39th, 9th to 11th Ave, and West 40th, 10th Ave to Dyer | Possible daytime delivery holds | Daytime | Set weekly |
During the Tenth Avenue closure, one eastbound lane between Eleventh and Tenth Avenues is to stay open, and flaggers are to keep pedestrian and bike access open. The West 40th closure is the longest-running item on the table. The October 20 advisory started it on October 26 and expects it to last through the end of the year, which is also when E-96's steel is due out. The Port Authority publishes exact dates week by week, so any of these windows can shift.
E-96 Is One Piece of About Seven Years of Loud Work
Clearing one ramp by New Year's does not mean the loud work is over. In an April 7 letter to the Port Authority, Manhattan Community Board 4 summarized how the project's Final Environmental Impact Statement breaks down foundation and demolition work. It adds up to about seven years:
- About 13 months for the decks over Dyer Avenue
- About 22 months for the ramps
- About 23 months for the storage and staging facility
- About 28 months for the main terminal
E-96 is the first of the existing bus ramps scheduled to come down, so this winter's demolition is the start of the ramp work. The Port Authority puts the end of phase one, meaning the Dyer Avenue deck, the storage and staging facility and the new ramp, at the end of 2030.
The work hours have already changed once. When CB4 wrote in April, overnight work ran five days a week from 11:30 p.m. to 5 a.m. The board reported that tenants came to its Transportation Planning Committee on March 18 to describe vibration and noise in their homes. It also named Mayberry and Covenant House as noise-sensitive buildings with no sound-measuring devices out front. It asked for fewer and shorter overnight shifts, more monitoring, and public reporting when noise limits are exceeded. W42ST covered the same concerns over the summer. Its June 9 story featured a resident of 555TEN, at Tenth Avenue and West 40th, whose home faces the roads and ramps by the Lincoln Tunnel, where a platform was being built over Dyer Avenue. W42ST's July 14 follow-up reported an indoor reading of 91 decibels with the windows closed just before midnight on July 7.
By July, the Port Authority's weekly notice said overnight hoe ramming would be kept to a minimum, most high-noise work would move to daytime, and acoustic blankets, temporary barriers and monitoring equipment would be used where feasible. The October E-96 plan follows the same approach, giving priority to daytime shifts and keeping the quieter cutting methods for nights.
The Green Space on These Blocks, Now and Later
The area's small existing green spaces are inside the work zone. In its 2024 environmental review, the Port Authority described Teresa's Park as a landscaped sitting area on Port Authority property with a gated entrance on West 39th Street. It sits just west of Metro Baptist Church at 409 West 39th. The Hell's Kitchen Neighborhood Association runs it as a community garden, and access requires a key obtained through Manhattan Community District 4. The same document describes Astro's Dog Run at Galvin Plaza, which the association maintains under a revocable permit.
Some of that open space is already in use for construction. New York YIMBY reported in August that a small community park on the south side of the Tenth Avenue exit ramp was holding equipment, and that the former bus parking lot on West 40th had become a staging area.
The Dyer Avenue deck-over between West 38th and West 39th, where steel rebar was going in by August, is where the larger promise will eventually be delivered. Before it becomes a park, though, YIMBY reported that the deck will serve as temporary bus staging while the rest of the construction continues. The Port Authority's project page promises more than 3 acres of public open space, along with fewer idling buses on city streets and outward-facing local retail. The deck becomes publicly accessible green space only after the terminal replacement is finished, and that terminal is scheduled for 2035.
Where the Weekly Schedule Lives
Because exact closure dates come out one week at a time, the most reliable source is the project's weekly notices page, where the week-by-week plans are posted. For questions, noise complaints or general information, the Port Authority lists [email protected] and (212) 435-5682. You can also sign up for project advisories by email through the same address or at pabtreplacement.com.
If you own a co-op or condo near Dyer Avenue and want to think through how a construction schedule running to 2030 and 2035 could affect the timing of a sale or a renovation, David Menendez can go over the specifics of your block with you. Let's Connect.